Oracle wants nuclear power for a massive data center. The company filed a new request on October 2. It targets power from Wisconsin’s Point Beach Nuclear Plant. The move was confirmed in Oracle’s own announcement.
Oracle seeks 125 to 250 megawatts of electricity. That is 10% to 20% of the plant’s output. The plant sits in Manitowoc County, according to NucNet. It has run safely for more than 50 years.

Point Beach Nuclear Plant Will Power Project Lighthouse
The power will supply Project Lighthouse in Port Washington. Project Lighthouse is a $15 billion AI data campus. Oracle is building it with OpenAI and Vantage Data Centers. Construction broke ground back in December 2025.
Oracle is not just renting space in Wisconsin. It is anchoring the state’s nuclear energy future. That is not a small footnote here. That is a line in the grid plan.
Why We Energies Customers Could See Lower Bills
We Energies already faces rising costs at the plant. Fuel costs alone will climb by $59 million in 2027. Total service costs there will rise $176 million that year. Oracle’s subscription would offset a real piece of that burden.
The savings estimate grows the further out you look. Oracle’s deal could save $300 million in fuel costs. That figure runs through the year 2033. More than one million Wisconsin customers would benefit.
Oracle’s Broader Commitment to the Port Washington Project
The arrangement still needs state approval first. Wisconsin’s Public Service Commission must sign off on it. Oracle says it will fully fund Project Lighthouse’s energy costs directly.
Project Lighthouse promises major economic impact for the region. Oracle expects it to generate over $11 billion locally. The project should create more than 4,000 construction jobs. It will also support 1,000 ongoing operations positions.
Workforce programs are part of Oracle’s pledge too. The company says it will invest in local infrastructure. Those commitments extend well beyond the power deal itself. They tie Oracle’s reputation to this one Wisconsin county.
Financial Scrutiny Still Surrounds the Deal
Oracle’s finances have drawn scrutiny over this project before. The company sued Wisconsin regulators over collateral requirements earlier this year. WEC Energy Group’s CEO addressed that dispute on an earnings call.
He said Oracle is now meeting the new requirements. The claim comes via Wisconsin Public Radio.
Oracle remains committed to paying its full share, the CEO said. That comes as OpenAI’s own finances face separate questions elsewhere. Both companies are tied to this single Wisconsin campus.